Coinciding with the 19th Day of the first month of the Fire Male Monkey Year, the distribution network asset worth Nu.124.045 M was taken over by BPC from DGPC on 26th February 2016. The handing/taking over document of the assets was signed by Mr.Yeshey Tenzin, Chief Engineer, Tala Hydro Plant, DGPC, Rinchentse and Mr. Sandeep Rai, General Manager, DCSD, BPC, Thimphu at the THP, DGPC office in Rinchentse in presence of officials from BPC, Phuentsholing and DGPC. The effective date of taking over of the assets will be from 1st July 2016. With the taking over of the distribution network system, the customer base of ESD, BPC, Phuentsholing will increase by over 600 customers.
↧